staggered manner. Initially, construction will be taken up on
stretches with wide roads, especially Miyapur-Panjagutta,
Nagole-Mettuguda and LB Nagar-New Market. Simultaneously, carriageway
will be widened on narrow parts of the metro rail corridors.
These decisions were taken at a joint coordination-cum-review meeting
held by Hyderabad police commissioner A K Khan on the Traffic
Management Plan for the metro rail works with Hyderabad Metro Rail MD
N V S Reddy, traffic police of Hyderabad and Cyberabad, GHMC,
Concessionaire L&T and traffic experts here on Tuesday.
held by Hyderabad police commissioner A K Khan on the Traffic
Management Plan for the metro rail works with Hyderabad Metro Rail MD
N V S Reddy, traffic police of Hyderabad and Cyberabad, GHMC,
Concessionaire L&T and traffic experts here on Tuesday.
Traffic consultants for L&T made a presentation on the detailed road
inventory of metro rail corridors and the proposed traffic management
action plan to minimise inconvenience to commuters during the metro
rail construction activities.
inventory of metro rail corridors and the proposed traffic management
action plan to minimise inconvenience to commuters during the metro
rail construction activities.
At the meeting, the Metro Rail MD explained the construction plan,
which involves most of the construction activities being done in
Miyapur and Nagole casting yards with adoption of pre-cast
construction methods for both viaduct and stations.
which involves most of the construction activities being done in
Miyapur and Nagole casting yards with adoption of pre-cast
construction methods for both viaduct and stations.
Khan advised the traffic police to identify works required for
improving road surface on all corridors as well as on parallel and
alternative roads to enable smooth traffic flows during the
construction period.
improving road surface on all corridors as well as on parallel and
alternative roads to enable smooth traffic flows during the
construction period.