Deccan Chronicle
The HMDA is set to complete the phase IIA of the Outer Ring Road in
May next year, six months ahead of schedule, officials said. Work
between Shamshabad and Pedda Amberpet is on in full swing. Officials
who inspected the works on Saturday said 40 per cent work was
complete.
“We asked the contractors to complete the work as early as possible,”
said Mr A. Suresh Babu, deputy general manager of the Hyderabad Growth
Corridor Limited. “Public money will be saved if the work is completed
ahead of schedule.”
The project has been taken up on build-operatetransfer mode and the
estimated cost of the second phase is Rs 2,439 crore. The 62.3-km ORR
PhaseIIA has been divided into five packages. Work is being taken up
between Narsing and Patancheru. After completion of the stretch, the
HMDA will shift its focus to the third phase.
HMDA officials said they had acquired land for the phase-IIB to avoid
delay in taking up the works. “Phase-IIB between Patancheru and Pedda
Amberpet will be taken up shortly with assistance of Rs.3,558 crore
from the Japan International Cooperation Agency,” he said.
The 71.3-km phase-IIB is being divided into six packages. The last
phase will cover Kandlakoi, Shamirpet and Ghatkesar. According to
officials, the civic body will develop intelligent transport mechanism
on ORR to ensure safe travel for the public. Toll fee will be
collected on the basis of the construction cost.